Carnival PARADISE

Carnival Cruise Line, ALMACO Group
Freeport, BAHAMAS

Scope of work:
Full refurbishment of deck 14 to new cabins area. Works such as: background outfitting works for new blocks + construction of 26 modular cabins before dry dock. During dry dock: construction of raised floor, steel welding works, New fire doors weldings, Loading of 26 modular cabins including construction of 10 stick build cabins on board from which 4 is forward Suite cabins. Insulation and other modification works in lower deck 12, to meet new layout. Including wallpapering works and new aerobics room construction. As well full outfitting of new passenger stairs through deck 12 to deck 14.

Manpower:
54 workers total (14 workers during block outfitting and 40 additional workers during dry dock).

Duration:
February 2018 – March 2017

 

Most Recent Projects